AALO, Mar 6: Power supply to at least nine districts will be affected as the Daporijo-Aalo 132 KV Transmission will go into a weeklong shutdown from March 9-12 and from March 16-19 from 0800 hrs to 1630 hours for carrying out clearance of vegetation along the corridor of transmission line and associated annual maintenance as the transmission line passes through tough terrain with thick forests.
The Pasighat Transmission Division has informed that the shutdown will affect the grid power supply during the day time to the downstream districts of Leparada, Lower Siang, West Siang, Shi-Yomi, Siang, Lower Dibang Valley, Namsai, Lohit and some parts of Changlang district. The Power Division has appealed to all consumers to bear with the inconveniences during the said periods and the department has assured to put in all out effort to restore it as early as possible. DIPRO